A local shop quotes $100 per part. An overseas shop quotes $60. On an order of 50 parts, the overseas quote appears to save $2,000. That figure tells you how much less the supplier charges for the parts. Your purchasing decision depends on what it costs to get 50 accepted parts to your receiving dock by the date your assembly team needs them. [Worked example]
Start by sending both suppliers the same drawing revision, material specification, tolerances, finish requirements, inspection scope, and quantity. Ask them to quote delivery to the same address and use the same required date. A quote that excludes anodizing, a dimensional report, or final delivery leaves costs for the buyer to pick up. A higher quote may already cover those items. [FSFAB]
Once the quotes cover the same job, calculate the delivered cost per accepted part. Then check what it would take for each supplier to deliver the full usable quantity on time.
1. Calculate the Delivered Cost per Accepted Part
Delivered cost per accepted part refers to the total cost of purchasing, receiving, and accepting a batch at a specified location, divided by the number of parts that ultimately pass inspection.
Use your factory, assembly site, or designated warehouse as the endpoint. An international freight quote can cover transport to a port or airport while leaving clearance, destination handling, and onward delivery for the buyer to arrange. A domestic quote can leave pickup and delivery to the buyer as well. Carry both quotes through to the same receiving address. [DHL]
For a completed batch, use the following calculation. Include quality handling and rework you paid for, then subtract refunds or credits you actually received. [Calculation framework]
Actual delivered cost per accepted part = (Purchase and setup costs + delivery costs + net inspection and quality costs) ÷ final accepted quantity
Before placing the order, use confirmed prices where possible and estimate the remaining costs. Add financing costs associated with payment or inventory and the expected cost of risks that the base estimate leaves open. Divide by the expected usable quantity. [Calculation framework]
Risk-adjusted cost per accepted part = (Estimated batch costs + financing costs + expected incremental risk costs) ÷ expected usable quantity
Keep the assumptions visible. For example, if your base estimate includes a $200 screening charge, and a defect could require an additional $500 of rework with a 20% probability, the additional expected rework cost is $100. If the base estimate already carries that $100 allowance, leave it there. A separate downside scenario can still show what your cash outlay would be if the full $500 were incurred. [Illustrative calculation]
The receiving deadline also changes how you use the result. A batch that produces 49 accepted parts can have a reasonable cost per accepted part even if your production team needs 50 to complete the build. A replacement arriving next week improves the final batch yield. It helps this week’s build only if the schedule has room for it.
Overseas sourcing can work well when the drawing is stable and the schedule leaves time for freight, inspection, and recovery. A local shop may offer more room to resolve a fit issue or remake a part before the build. The value of that room depends on your deadline and the cost of missing it. [XMAKE]
Action : Put actual batch cost, estimated risk-adjusted batch cost, and the required usable quantity and date in separate fields on your sourcing worksheet.
2. Put Both Quotes on the Same Cost Sheet
Quote normalization refers to putting supplier offers into a shared cost and scope format so each total represents the same finished part, inspection package, and delivery point.
Start with the drawing and the operations needed to make the part usable. For an aluminum mounting bracket, that could include material, machining, thread preparation, deburring, anodizing, and checks on finished dimensions. If one quote includes anodizing and the other leaves it to you, add the finishing charge, transport to and from the finisher, and any inspection you will have to repeat after the finish is applied. [FSFAB]
| Cost line | What to confirm |
|---|---|
| Parts and processing | Material grade and condition, machining, deburring, heat treatment, and surface finishing |
| Setup and tooling | Programming, workholding, special tools, first-article preparation, and which charges recur |
| Inspection and documents | Material certificates, dimensional reports, CMM reports where required, and receiving inspection |
| Packaging and delivery | Protective packaging, pickup, freight, insurance, destination handling, and delivery to the receiving address |
| Import charges | Brokerage, clearance fees, duties, and applicable taxes or surcharges |
| Payment | Quote currency, bank and conversion fees, deposit, balance due date, and financing cost |
| Quality and recovery | Sorting, rework, scrap, replacement parts, replacement freight, and credits or refunds |
Mark each line as included, separately priced, pending, or inapplicable. A blank line can hide a charge or cause someone to add a charge that was already in the unit price. Ask the supplier to itemize an ambiguous fee where it could change the decision. Record the quote currency and the exchange rate you used so you can reproduce the comparison later. [DHL; FSFAB]
For international quotes, capture the Incoterms® rule and the named place in writing. For a DDP quote, ask the supplier to name the full delivery address and confirm the charges it has included and how import clearance will be handled. Put any buyer-side unloading or receiving work in your own cost sheet where it applies. Confirm duties and import charges for the part classification, country of origin, destination, and import arrangement. Track any recoverable tax in the cash requirement and confirm whether your business can recover it before excluding it from the final cost. [DHL]
Keep separate columns for the first order and a reorder. If a shop charges $800 for programming and fixtures on the first 50 pieces, that adds $16 per ordered part to that batch. If a confirmed repeat order uses the same fixture and has a $200 setup charge, that adds $4 per ordered part on a second batch of 50. Ask how long the shop will retain the fixture and whether a revision or a long gap between orders triggers a new charge. Base the first-order decision on the quantity you have authority to buy. [Illustrative calculation; FSFAB]
Action : Send the same RFQ and cost sheet to both suppliers and resolve any pending line that could change the order decision.
3. Estimate How Many Parts Will Pass Acceptance
Usable yield refers to the share of received parts that meet the agreed acceptance criteria after inspection and any approved rework.
Write down what counts as a pass before using a supplier’s yield estimate. Two shops can report different pass rates because they inspect different features or use different sampling plans. For a machined housing, agree on the critical bore and its datum, the measurement method, the inspection stage, and the required records. If a dimension applies after coating, make that explicit. Confirm whether you need a material certificate, a first-article report, or measurements for every part on a critical feature. [XMAKE]
For an incoming batch, a simple forecast is:
Expected accepted quantity = Received quantity × [First-pass acceptance rate + (1 − first-pass acceptance rate) × rework recovery rate]
The rework recovery rate applies only to parts that fail the first inspection. Suppose 50 parts arrive and 46 pass on the first inspection. If approved rework recovers two of the four failures, the final accepted quantity is 48. Add the cost of reworking and reinspecting the two recovered pieces. The two scrapped pieces still incurred purchase and freight costs, which stay in the numerator. If approved rework finishes after your build date, the on-time accepted quantity remains 46. [Illustrative calculation]
Handle replacement parts the same way. Add them to the accepted count once they pass, and count any extra freight, inspection, or other charges you actually bear. If the supplier credits the cost of rejected parts, record the credit against the batch. A commitment to remake defective parts can help, but the purchase order needs to specify who pays for replacement freight, how quickly the supplier will start the remake, and how the replacements will be released. [XMAKE]
Use records from comparable jobs where available. A supplier’s performance on an unfinished turned spacer tells you little about a thin-walled part with several critical features and a finish applied by an outside processor. A first-article approval can confirm whether the shop understands the drawing and can document the agreed checks. A pilot batch adds evidence about consistency across several parts. For a first order with limited evidence, run the comparison across a range of accepted quantities and see how many failures the budget and schedule can absorb. [XMAKE]
Decide which question you are answering before choosing the denominator. For batch economics, divide by the number of parts that batch ultimately yields. For a requirement of 50 accepted parts by a fixed date, add the cost of covering the shortage and divide by 50 once the recovery plan can credibly meet the date. Use the same requirement for both suppliers. [Calculation framework]
Action : Agree on inspection and replacement terms before issuing the purchase order, then record first-pass accepted, recovered, and on-time accepted quantities separately.
4. Work Through a 50-Part Local vs. Overseas Quote
A worked quote comparison refers to applying the same cost, yield, and delivery assumptions to each bid to see where their rankings change.
In this example, both suppliers quote 50 pieces to the same receiving site. All figures are in US dollars. The prices, acceptance quantities, and risk allowances are hypothetical. [Worked example assumptions]
| Cost or outcome | Local supplier | Overseas supplier |
|---|---|---|
| Ordered quantity | 50 | 50 |
| Quoted unit price | $100 | $60 |
| Parts subtotal | $5,000 | $3,000 |
| Programming, fixtures, and other setup | $500 | $800 |
| Packaging, freight, and insurance | $100 | $650 |
| Nonrecoverable import charges and clearance | $0 | $350 |
| Inspection | $200 | $400 |
| Estimated batch cost before risk allowance | $5,800 | $5,200 |
| Expected final accepted quantity | 49 | 46 |
| Delivered cost per accepted part before risk allowance | $118.37 | $113.04 |
| Additional financing and expected risk costs | $100 | $600 |
| Risk-adjusted cost per accepted part | $120.41 | $126.09 |
The overseas unit price is 40% lower. Once setup, freight, clearance, and inspection are included, the $2,000 difference in parts price falls to $600 in estimated batch cost. The overseas batch still costs less per accepted part before the financing and risk allowance. When those allowances are included, the local batch comes out $5.68 lower per accepted part. [Worked example calculation]
I recalculated both quotes and then tested the cost of getting all 50 parts on time. I held the local top-up cost at $140 for its one missing part and varied the overseas top-up cost for its four missing parts. The two plans tied at $120.80 per usable part when each overseas replacement cost $60 all-in. At $40 per overseas replacement, the overseas plan cost $119.20 per usable part. At $140, it cost $127.20. That calculation gave me a specific number to check against a backup quote. [Sensitivity calculation]
That test starts with the risk-adjusted batch totals of $5,900 and $5,800 and assumes the top-up costs are additional. If either risk allowance already includes the cost of filling the same shortage, deduct the overlapping amount before adding top-up costs. The example also assumes the missing quantities are known and that the backup parts can be delivered and accepted on time. An actual recovery quote may include its own minimum charge, programming fee, and expedited finishing. A $60 break-even point only helps if the supplier can cover all four parts at a total incremental cost of $240 and meet the date. [Sensitivity calculation]
Action : Calculate the maximum you can spend to cover the expected shortage, then compare that number with a written backup quote that includes finishing, inspection, and a delivery commitment.
5. Test the Schedule Before You Award the Order
Scenario analysis refers to recalculating each sourcing plan under different cost, quality, and timing conditions to see whether it can meet the same purchasing requirement.
Run three cases for each supplier. In the base case, use confirmed quote items, a realistic door-to-door transport plan, and yield evidence from a comparable job or pilot. In the downside case, model one credible event, such as a failed first article, a rework cycle after arrival, or a missed collection. Update both the cost and the date. In the on-time full-quantity case, price an executable way to have your full accepted quantity ready by the deadline. That may involve a reserved production slot, a small parallel order, or expedited shipping for a replacement batch. [Calculation framework; XMAKE]
Build the timeline backward from the day the parts have to be usable. Allow time for drawing clarification, material availability, production scheduling, machining, outside processing, first-article approval, and final inspection. Show the activities in the order the shop will perform them. Then add packing, pickup, transit, customs clearance if applicable, receiving inspection, and internal release. Ask when the supplier’s quoted clock starts and how much recovery time remains if a critical dimension fails inspection. [XMAKE; DHL]
For example, suppose your build needs accepted parts on day 20 and receiving inspection takes two days. The batch must reach your dock by day 18. If transport and clearance are scheduled to take six days, the batch must be ready for collection by day 12. A two-day delay in first-article approval uses two days of any remaining schedule margin. If the plan has zero margin, ask what can be moved and what that change costs. Splitting off an urgent quantity can be worth pricing if the first build needs only a portion of the batch. [Illustrative schedule]
You can enter a probability-weighted allowance for ordinary disruptions. For a fixed build date, also check whether the fallback can physically meet the deadline. A low expected loss offers little help if the only replacement slot is after assembly. A stable repeat part with enough time for a pilot and regular replenishment may favor an overseas source. A revision-prone part tied to a commissioning date may justify a local fallback even if the base-case overseas quote is cheaper. [XMAKE]
Action : Put the delivered cost per accepted part, cost to meet the full on-time requirement, and latest acceptable dock date side by side on the award sheet. Give the buyer and supplier a date to trigger the fallback while it can still meet the build.
Foire aux questions
R : Check that both quotes cover the same drawing revision, quantity, finish, inspection documents, and delivery address. Add any missing charges, then divide each total by the expected accepted quantity. If the build date is fixed, price how each supplier would cover a shortage by that date. [FSFAB; DHL]
R : DDP helps define the supplier’s delivery and import responsibilities at the named destination. Calculate your cost per usable part separately by including applicable buyer-side receiving, inspection, and quality costs, then dividing by the accepted quantity. Confirm the named address and the charges included in the quote. [DHL]
R : Charge the first batch for the programming and fixtures you actually have to pay for. Model the reorder using the supplier’s confirmed recurring setup fee, fixture retention terms, and charges for any drawing changes. Keep the first-order and repeat-order totals visible. [FSFAB]
R : Ask for inspection results from similar work and use a pilot batch when timing allows. With limited evidence, model a range and calculate how many parts can fail before the sourcing decision changes. For a deadline-driven purchase, count only parts you expect to accept by the required date. [XMAKE; calculation framework]
R : It can be the better buy when the local shop’s faster inspection, revision turnaround, or replacement delivery makes it cheaper to satisfy the full requirement. Compare the higher purchase price with the price and timing of a credible recovery plan for the overseas order. [XMAKE]
R : It is worth testing when the drawing is stable, the acceptance criteria are clear, and the schedule can accommodate first-article approval, transport, and a recovery window. Use the pilot to measure the accepted yield and the time from order release to usable parts at your site. [XMAKE]